Major Construction Projects
Questions? Call Physical Plant Engineering Services @ 453-6777
| Design | Out for Bid | Work in Progress | Jobs Complete |
| Status | Title | Funding Source/FY | Description |
| Design | Replacement of Air Handlers in the Tech Complex | Estimate being developed | This project will research the replacement of the air handling units in Technology A, B, C & D located in the stair towers. An initial investigation has been completed. The project is currently on hold. |
| Design | Replace High Voltage Electrical System-Phase IV CDB Project #825-020-144 |
$300,000 (FY04 Capital Renewal) Total Budget $3,000,000 |
This is the fourth of a multiphase project. BRIC Partnership was selected via QBS. The project is on hold pending funding. |
| Design | Campus Water Line Replacement CDB project #825-020-140 |
$200,000 (FY04 capital renewal) | This project will be the first of multiple phases to replace parts of the campus water distribution system. Water lines targeted for replacement consist of four to twelve inch mains ranging in age from 40 to 100 years. Lines in most urgent need of replacement are those serving Wham/Pulliam Hall, old Campus, Thompson Point, Engineering and the Agriculture Building. This project will replace aging domestic water lines within several areas on campus. Cochran & Wilken was selected via QBS. Design is complete. The project is on hold pending funding. |
| Design | Coal Storage and Handling System CDB project #825-020-145 |
$3,300,000 | The project will include a coal receiving system, a contained storage silo, and a plant feed system as well as associated site work. Funding will come from a combination of DCEO grant funds and state appropriated monies available to the Carbondale campus. BRIC Partnership is the design consultant. The project is on hold pending funding. |
| Design | Roof Renovations-various buildings CDB project #825-020-142 |
$500,000 (FY04 capital renewal) | This project will replace roof membranes on various buildings. In all, the University owns approximately 525 buildings with a wide variety of roofing materials. As roofs are replaced, a concerted effort is being made to provide additional slopes on roofs for smaller buildings by using pre-manufactured trusses and standing seam metal. Poirier & Associates were selected via QBS. The project is on hold pending funding. |
| Design | Transportation Education Center CDB Project #825-020-143 |
$60,649,300 FY09 Ramp |
This project will provide combined facilities for Automotive and Aviation Technology programs. The facility will be constructed at the Southern Illinois Airport. The design team is completing bid documents which will include the office block, dispatch center and auditorium. Pending release of funds, construction is expected to begin spring 2010. |
| Design | General Core Curriculum Classroom Building | $18,000,000 | This project will construct a student orientated educational facility to serve SIUC's core educational programs planning. Planning approval was received at the September 14, 2006 BOT meeting. This project on hold. QBS process has been suspended. |
| Design | Student Services Building | $25,000,000 | This project will construct a student-orientated service facility to serve SIUC's students, parents, and alumni. Planning approval was received at the September 14, 2006 BOT meeting. White & Borgognoni is beginning program analysis phase. Final site selection will be presented to the BOT general discussion meeting September 11, 2008. Preliminary design concepts are being developed. |
| Design | Wind Generation Study | $10,000(SIUC) $30,000(ICECF) |
SIUC is partnering with Illinois Clean Energy Community Foundation (ICECF) to study the feasibility of wind generation on the Carbondale campus. Currently ICECF has approved funding along with SIUC commitment to begin initial evaluation. This study will acquire site specific wind data to determine power generation feasibility. Wind instrumentation has been installed on the WSIU Radio Tower and data is being collected. |
| Design | Research Park Interior Roadway | $1,250,000 | This project will design and construct additional roadways at the Southern Illinois Research Park. This improvement will allow future facility development within the SIRP campus. Project was approved at the September 20, 2007 BOT meeting. A/E selection via QBS was awarded to Hurst Rosche. Design is underway. IDOT will bid project in early 2010 for a spring construction start. |
| Design | Access Control & Security Cameras Allen & Boomer Halls GIR #08292 |
$390,000 | This project will install access control and security cameras at all exterior entries to Allen and Boomer Halls. BOT approval was requested at their September 11, 2008 meeting. The project will be designed by Engineering Services. This project was cancelled by Glenn Stine on January 21, 2009. |
| Design | Roof Replacements General Campus |
$2,500,000 | This project will replace roof systems for six campus facilities (Quigley, Pulliam Hall/Pulliam Industrial, Physical Education, Environmental Health and Safety, and Laundry Building. Projects will be funded via Facilities Maintenance Fee and Deferred Maintenance funds. BOT approval will be requested at the December 2009 BOT meeting. |
| Design | Grand & Wall Street Apartment Complex Flooring GIR #10096 |
$610,000 | This project will provide new flooring to replace failing stained and sealed concrete finish. Common areas will be carpeted. Apartments will be tiled. This project is pending approval at the December BOT meeting. |
| Design | Primary Electrical Upgrades | $1,250,000 FMF |
This project will upgrade the primary electrical infrastructure on the general campus to improve the integrity of specific transmission segments serving major campus facilities. This project is pending approval at the December BOT meeting. |
| Design | Replace Farm Service Center for College of Ag for Storm Damage GIR #10031 |
$478,455 | Project is currently in design with PPES and Eggemeyer Associates. Bid package should go to Purchasing in November or December. |
| Design | Repair Feed Mill for Storm Damage College of Ag GIR #10032 |
$550,000 | Project is currently in design with SKS Engineers, Decatur, IL. Project and budget approval is anticipated at the December BOT meeting. |
| Design | Repair & Upgrade Several Campus Elevators GIR #09018 |
waiting on estimate | Image, Lemp Elevator Consultants, and BRIC are preparing bid documents for repair and replacement of five campus elevators with deferred maintenance. |
| Design | Renovate and Upgrade Existing Passenger Elevator in Student Center GIR #10004 |
$290,000 | Image, Lemp Elevator Consultants, and BRIC are preparing bid documents for renovation to existing passenger elevator. |
| Back to the Top |
| Out for Bid | Football Stadium/Arena Renovation & Expansion |
$2,250,000 Scoreboard | Bid packages 1, 2, 3, 4, and 5 have been bid and have been approved by BOT. Scoreboard RFP proposals have been received and are being reviewed. Purchasing is finalizing the award package. |
| Our for Bid | Sprinkler Installation Thompson Point & University Hall - Phase III Bailey & Smith GIR #10113 |
$3,000,000 | Phase III project will design and install automatic sprinkler systems for Abbott, Bailey and Smith Halls located at Thompson Point complex and in University Hall located at 1101 S. Wall St. The design was completed by BRIC Engineering, LLC. Phase III will be completed the summer of 2010. Bids opened on 11-10-09. Contracts to be awarded at the December 10, 2009 BOT meeting. |
| Our for Bid | Recreation Center Replacement Generator GIR #09288 |
$143,000 | This project will install a new 125 Kw diesel emergency generator at the SRC to replace the existing failed generator. The new generator will be installed on the south side of the building. The entire project will be bid to outside electrical contractors. The project is at Purchasing as of 11-12-09. |
| Back to the Top |
| Work in Progress | New Ethanol Tank Travel Service GIR #09104 |
$144,620 | This project is to install a new 5,000 gallon buried ethanol tank at Travel Service, along with the installation of new digital fuel dispensers. The project was bid to outside contractors on 10/06/09. The low bidder was Illinois Oil Marketing Equipment, Inc., of Pekin, Il. PPES has recommended issuing a contract to the low bidder. Work to begin mid December. A pre-construction meeting was held 11-03-09. The contractor is expecting to start work approximately the middle of December and take 4-6 weeks to complete. |
| Work in Progress | Renovate Labs for Geology Dept. Parkinson Hall GIR #09174 |
$150,000 | This project will renovate laboratory 201B and 201F to accommodate a new faculty member in the Geology Department. The work is being done by Physical Plant trades and got underway September 2009. Work continues with completion expected by mid-December 2009. |
| Work in Progress | Schneider Hall Replace exisiting emergency generator GIR #09117 |
$180,000 | PPES will provide construction documents. PSO electricians will do the installation. A portable generator has been rented for use at Schneider Hall during construction. Work began by PSO electricians in August. Work to be completed on December 1, 2009. |
| Work in Progress | Pave and expand parking lot #58 GIR#08315,GIR#09124 |
$240,000 | This project will pave and expand parking lot #58 adjacent to Grinnell Hall for Parking Division. Bidding took place in July. E.T. Simonds awarded bid for general work and All Electric is awarded bid for electrical work. Construction to take place August, September, and October 2009. Construction is 98% complete. Punch list being addressed. |
| Work in Progress | Faner Roof Replacement | $2,500,000 | This project will replace approximately 65,540 square feet of roofing. BOT approval was received April 10, 2008. White & Borgognoni is under contract to provide the design and bidding documents. The project will be funded by the Facility Maintenance Fee. BOT award of contract was April 2, 2009 to the low bidder, Jim Taylor, Inc. for $2,143,789. Work began on May 18, 2009. Expected completion date is November 18, 2009, weather dependent. Punch list to follow. TPO Roofing complete. Sheet metal complete 11-25-09. |
| Work in Progress | Football Stadium/Arena Renovation and Expansion | $73,500,000 Total Phase 2 $2,518,732 Awarded Bid Pkg. 2 22 contracts $28,000,000+ Bid Pkg. 3 16 contracts $10,000,000+ Bid Pkg. 4 2 contracts Est. $1,350,000 Bid Pkg. 5 5 contracts Est. $4,163,000 Scoreboards Request for Proposal (RFP) 1 contract Est. $2,250,000 |
Saluki Way - Phase I Litton Enterprises: Site Utilities ($914,585) F.W. Electric: Site Electric and Telecom ($250,285) Saluki Way - Phase II Fager/McGee Const.: Arena and Athletic Building Demolition and Concrete Construction: ($2,324,900) This contractor has been able to do some minor demolition in the Arena and has been doing preliminary layout for major floor demolition in the future. Bid Package #2 - 22 contracts awarded February 12, 2009.
Stadium and Site Project Update November 6, 2009:
2-Week Outlook: Arena and Athletics Building:
Stadium and Site:
Contract completion date: November 15, 2010 Substantial completion date:
|
| Work in Progress | New Cage and Rack Washer Life Science II GIR#08201 |
FY08 $185,500 |
This project includes the purchase of a new cage and rack washer. The demolition of the existing washer and the installation of the new washer will be performed by SIUC Physical Plant personnel. Project was slated for completion the week of August 24, 2009. Vendor is completing punch list items. |
| Work in Progress | Exterior Campus Signage GIR#04308 |
$1,000,000 | This project will develop way-finding signage on campus. This will include main entry, roadway directional signage, informational kiosks, and building identification signage. BOT reviewed the signage renderings at their July 8, 2004 meeting. Bid ADA Map Signage specifications for campus directional, kiosk and building identification signs have been developed and final quantities for both academic and auxiliaries are complete. Bids were received on January 10, 2006. Funding determinations for auxiliaries have been approved. Remaining signs have been received for installation. The current scope of work is substantially complete. |
| Work in Progress | Morris Library Renovation & Addition CDB Project #825-020-129 |
$54,022,325 | This project will include renovation of the existing library and construction of an approximate 50,000 gsf addition. Phillips Swager Associates, Inc. was selected via QBS process to complete the design for this project. In November the Governor made a commitment to release the construction funds for this project. Bids were open for the MEP on September 21, 2005 and bids from General Contractors were opened on September 28, 2005. Initial ventilation bids were rejected by CDB and re-bid November 17, 2005. The successful bidders were: River City Construction (General) $19,651,000; Southern Illinois Piping (Plumbing) $789,000; Automatic Fire Sprinkler (Sprinkler) $857,700; Southern Illinois Piping (Heating) $4,398,000; France Mechanical (Ventilation) $3,887,000; Brown Electric(Electrical) $4,088,629. The general contractor moved on-site February 6, 2006 and commenced site work and selective demolition. Entry Plaza/Water Feature (Phase II) bids were opened on March 22, 2006. The successful bidder was: River City Construction (General) $555,000. This project is substantially complete. Contractors are completing punch list items. Working through project closeout. Fountain has been started up and awaiting lighting adjustments. Elevator #4 repair work has commenced. Inspection has tentatively been scheduled for July 8th. Tower roofing replacement has commenced. Work scheduled to be complete in five weeks. Tower roofing replacement completed; final inspection completed. Elevator #4 work has completed. Final inspection completed. Waiting on CDB closeout. |
| Work in Progress | Chancellor's Classroom Improvements GIR#07057 |
FY06 $1,000,000 FY07 $500,000 |
This project will continue the renovation of auditoriums and classrooms throughout campus. The original project began in FY03. FY06 funds completed auditorium renovations in Davis Auditorium located in Wham and Muckelroy Auditorium in the Agriculture Building. It will also continue classroom furniture replacement and technology improvements throughtout campus. Auditorium renovations in rooms 240 and 440 of the Neckers Building began summer of 2006. New flooring, seating, lighting, and painting is complete in the Neckers Auditoriums. New classroom chairs and instructor's podiums have been provided in the general classrooms in Pulliam and Quigley. Neckers auditoriums are complete. Due to campus budget reviews, the remainder of FY07 projects are on hold. |
| Work in Progress | Football Stadium/Arena Relocation & Expansion Relocate Playfields |
$1,300,000 | This phase of the Saluki Way Football/Arena project will relocate the playfields and construct two new tennis courts. Contracts were approved at the July 10, 2008, BOT meeting. Contracts were awarded to the following: General (Schimpf Construction) $183,225, plumbing (Litton Enterprises) $116,290, electrical (W.J. Burke) $223,050, excavation (Mathis & Sons) $548,988.91. Relocation of the ballfields is substantially complete. All grading at the new location, south of the Motorcycle Safety Course, is complete including respreading of topsoil. The infield mix has been created and has been distributed to the three infields that were made. Work at the tennis courts and playfields is substantially complete. |
| Work in Progress | Power Plant Roof Replacement | $125,000 | This project will replace the roof on the original Steam Plant. Facility Maintenance Fee funded. Lakeside Roofing is low bidder. Construction has started. Walk-thru for punch list is to take place on October 21, 2009. Miscellaneous punch list items and change order yet to do. |
| Back to the Top |
| Jobs Complete | Sprinkler Installation Thompson Point & University Hall-PHII GIR #09001 |
$7,750,000 | Phase II project will design and install automatic sprinkler systems for Thompson Point, Felts, Baldwin, Kellogg and Warren Halls. The design was completed by BRIC Engineering, LLC. The project was bid 11/19/08. PHII will be completed the summer of 2009. The BOT awarded the following contracts at their December 11th BOT meeting: Morgan Commerical (general) $428,000; H.E. (plumbing) $119,500; Clinton Electric (electrical) $188,000; Continental Fire (sprinkler) $447,300. Project has been completed. |
| Jobs Complete | Housing-Grand & Wall Street Apartment Complex GIR#05291 |
$26,400,000 | This project will develop an apartment sytle housing complex on the corner of Grand and Wall Street.
The complex will provide 2 and 4 bedroom apartments with a total bed count of 400. Project approval was given at the February
2004 BOT meeting. Phillip Swager was selected via the QBS process. Pre-bid was May 25, 2005. Bid date was June 16, 2005. Contractor and University have reached agreement on outstanding disputes. Agreement being handled by change order. Waiting on O&M manuals and as-built drawings. Work to provide air supply/return to end lounges has been completed. Work to provide exhaust fans in apartment bathrooms has been completed. |
| Jobs Complete | Davies Gym Roof Replacement | $235,000 | This project will replace the roof for the Davies Gym building. Facility Maintenance Fee funded. Bids have been received with Geissler Roofing Co. as low bidder. Construction is complete except punch list and walk-through. This project is complete. |
| Jobs Complete | Law School Tennis Courts Renovation | $110,000 | This project will repair and resurface the tennis courts located at the Law School activity area. The six tennis courts there will be the replacement tennis courts for the six courts located south of the Physical Plant that are being demolished as part of the first phase of Saluki Way. Construction is complete. |
| Jobs Complete | Thompson Point Electrical Upgrade GIR#08094 |
$700,000 | This project will upgrade the electrical systems at Abbott and Smith Halls. Design will be completed by PPES. The project was approved at the January 17, 2008, BOT meeting. The project will be constructed summer 2009. Contract award will be requested at the February 12, 2009 BOT meeting. Low bidder is Clinton Electric ($333,007). Preconstruction meeting was held February 23, 2009. Work began May 12, 2009. Project is substantially complete. Work is complete. |
| Jobs Complete | Agriculture Building Roof Replacement | $600,000 | This project will replace areas C and D of the Ag Building roof. BOT approval was received on April 10, 2008. Ittner Architects is under contract to provide the design and bidding documents. The project will be funded by the Facility Maintenance Fee. BOT award of contract was April 2, 2009 to the low bidder, Kehrer Brothers, for $429,210. The project is now 100% complete. Waiting on warranty. |
| Back to the Top |