This project will replace the roof for the Davies Gym Building. Facility Maintenance Fee funded.
Near Term Expected Work
Punch list to be completed as well as walk-through.
Monthly Progress - July 2009
Construction to take place this summer.
Monthly Progress - June 2009
Status changed to a "Work in Progress"
Monthly Progress - May 2009
Bids have been received with Geissler Roofing Co. as low bidder. Purchasing is processing the contract paperwork.
Monthly Progress - April 2009
Purchasing has the construction documents and will receive bids on Thursday, April 16, 2009.
Monthly Progress - March 2009 Bidding is anticipated later this spring.
|