Schneider Hall - Replace Existing Emergency Generator

 

 

Quick Facts
Architect: PPES
Contractor: PSO Electricians
Status: Work in Progress
Project Costs: $180,000
Construction Dates: Start Date: August 2009 Completion Date:
Description
PPES will provide construction documents. PSO electricians will do the installation. Since Schneider Hall will be occupied by CIY during the summer, the campus portable generator will be connected to the electrical system during construction (summer 2009) to provide emergency back-up power.

Monthly Progress - August 2009
A portable generator has been rented for use during construction. Work has begun by PSO electricians.

Monthly Progress - July 2009
Installation is still on hold.

Monthly Progress - June 2009
The campus portable generator is being used at the SRC indefinitely. The installation of the new Schneider generator is "on hold" until the portable generator can be relocated to Schneider Hall. The Schneider generator has been ordered and will be stored when it arrives on campus.

Monthly Progress - May 2009
Asbestos removal completed. Purchase Order to be sent out on May 12, 2009. Shops to arrive asap.

 